These documents are for the purpose of preparing bids for projects. No other use is authorized by Matous Construction. Matous Construction is not the owner or creator of these documents and is not responsible for the completeness or accuracy of them. Bidders must satisfy themselves they have the latest and correct information. Downloading documents & files constitutes proof of agreement to these terms.

  • Salado WSC Kempner Pump Station

    Owner: Salado WSC

    Engineer: Walker Partners

    Estimate: $2,400,000.00

    Bid Date: July 1, 2026

    Project Description: This construction project generally consists of the following work: 

    Qty           Description
    1                4 Pump Variable Speed Package Pump Station
    1                CMU Building
    1                Electrical
    1                Site Improvements

    Document(s): 

    Proposals at due no later than Monday, June 29th at 4:00pm.

  • Hornsby Bend Biosolids Management Plant Headworks Improvements

    Owner: City of Austin

    Engineer: STV, Inc.

    Estimate:$24,099,300.00

    Bid Date: July 30, 2026

    Project Description: This construction project generally consists of the following work: demolishing the existing Headworks and constructing a replacement Headworks. The new Headworks will increase screening capacity, provide odor control, & replace critical screening and electrical infrastructure that are severely corroded & unsafe. 

    Document(s): 

    Proposals at due no later than Tuesday, July 28th at 4:00pm.